| September 2009 | ||||||||||||||
![]() |
||||||||||||||
| North side of the house Exterior is nearly finished, siding, windows, roofing trim are all in place. The siding and trim has been painted |
||||||||||||||
![]() |
||||||||||||||
| South side Gutters are in place, we are now working on a design for the posts and railings. We are also designing the patio and gardens near the walkout. |
||||||||||||||
![]() |
||||||||||||||
| Drywall is being loaded into the upstairs window, set in the loft and will be hung in the loft and great room | ||||||||||||||
![]() |
||||||||||||||
| The stairs going to the loft. Insulation has been installed, we used a foam skim coat and then filled the rest of the cavity with cellulose for a great fit. Electricity has been run and drywall will soon be hung. | ||||||||||||||